Projects / Drinking water

60 m³/day of drinking water for PRONACA, from well water

We designed, supplied, installed and commissioned a complete oxidation, sedimentation, multimedia filtration and ultrafiltration plant that makes the water drinkable in accordance with standard INEN 1108-2020.

  • ClientPRONACA
  • Year2024
  • IndustryFood
  • ScopeTurnkey project

TurbiMax 101 and SaniCarb 850Filtration ahead of ultrafiltration

Well water with iron and manganese, turned into drinking water

PRONACA needed to treat 60 m³/day of well water and remove metals such as iron and manganese, organic compounds and suspended solids to meet the INEN 1108 drinking water standard.

  • Dissolved metalsIron and manganese that give the water color and taste.
  • Organics and solidsOrganic compounds and suspended solids in the well water.
  • Controlled microbiologySafe drinking water for a food plant.
  • 60 m³/dayof drinking water
  • 2,000 litersoxidation and settling hopper
  • 0.02 µmultrafiltration barrier
  • 5,000 litersbackwash and CIP tank

Treatment train: from the well to drinking water

Six stages: first the metals are precipitated, then the water is filtered, and ultrafiltration blocks bacteria and viruses.

  1. Oxidation and settlingDiaphragm pumps dose oxidant and coagulant, and a hopper with online ORP precipitates the metals and organic matter.2,000 L hopper
  2. Pumping and buffer tankA horizontal centrifugal pump takes the settled water from a buffer tank to filtration.200 L tank
  3. Sediment filtrationTurbiMax 101 aluminosilicate media that retains the solids left by oxidation.Larger than 5 µm
  4. Activated carbonSaniCarb 850 removes oxidants, organic matter, color, odor and taste.Color, odor and taste
  5. UltrafiltrationA membrane that acts as an absolute physical barrier, even for bacteria and viruses.0.02 to 0.03 µm
  6. Backwash and CIPReinforced polyethylene tank on an SS304 stainless steel frame, with a dedicated pump.5,000 L tank

Automation and control

  • Horner PLC with 2.2″ HMI screen and IP65 protection rating.
  • Online ORP monitor to control oxidation and settling.
  • Turbine flowmeter, pressure gauges, pressure switches, 2- and 3-way actuated valves and a compressor for air-assisted UF backwashes.
  • Pressure alarms
  • Tank level
  • Motor thermal protection
  • Air backwash

Complete turnkey plant

Sanitron designed, supplied, installed and commissioned the complete plant, trained PRONACA’s operators and handed it over with a one-year warranty.

What Sanitron did

  1. Detailed engineeringSizing and design of the complete potabilization train.
  2. SupplySettling tanks, pumps, fiberglass tanks, filter media and UF membranes.
  3. InstallationElectromechanical installation, control panels and hydraulic and pneumatic piping.
  4. CommissioningStart-up tests, parameter setting, training and handover with a one-year warranty.

Results

  • 60 m³/day of drinking waterStable production in accordance with standard INEN 1108-2020.
  • Metals and pathogens removedOxidation, coagulation, multimedia filtration and ultrafiltration combined.
  • Continuous operationAutomation that reduces the risk of unexpected shutdowns.

Does your food plant need drinking water from a well?

We design tailor-made potabilization and ultrafiltration systems, with precision automation and local technical support.

Contact us

Office in EcuadorDe los Eucaliptos E8-70 y calle E9, Quito 170307

Phone+593 99 871 1330
+593 2 280 8126

Emailinfo@sanitronec.com

Office hoursMonday to Friday
9:00 a.m.–12:00 p.m. and 1:00–6:00 p.m.

Office in the United States9995 NW 9th St. Circle, Suite 3, Miami, FL 33172
+1 786 972 2008